Remediation & Demolition, Gloucestershire

Sector: Industrial
Service: Construction
Location: Gloucestershire
Value: Undisclosed
Duration: 12 weeks

Project Background

Following a decision by the Client to divest of its interest in this restricted airfield site, H Sweet were contracted to deliver remediation and demolition works at Cotswold Airport, returning the site to its original condition.

Our Approach

Working closely with the Client team, stakeholders and relevant statutory bodies, H Sweet took a meticulous approach to planning the works which required identification of below ground site wide services and contention with site wide restrictions to deliver this package of remediation in an efficient and timely fashion.

The Outcome

The works were completed to specification and on time, ensuring our Client was able to relinquish its commercial commitments as required, with no impact on its day to day operations.

Related Content

News

CHSW Christmas Message

Christmas Opening Hours

Christmas opening hours 2018

Read more

News

Lewis Sweet_Mike Sweet_Dan Sweet_Gareth Sweet at Clipper Gala Dinner

Clipper Gala Dinner raises over £10,000 for nominated charities

H Sweet and Sons are delighted to report that our recent Clipper Gala Dinner raised in excess of £10,000 for Children's Hospice South West and Unicef.

Read more

News

Clipper_race_yachts

H Sweet and Sons hosts Clipper Gala Dinner

H Sweet and Sons are delighted to host a Clipper Gala Dinner on 9th March at the Bristol Marriott Royal Hotel, in support of Chairman, Mike Sweet.

Read more